  • Drywall at 90%
  • 1st floor complete
  • Carpet install to commence
  • Pro shop ready for fixtures
  • Cart barn charger system installed – ready for chargers
  • Service elevator installed
  • Passenger elevator at 75%
  • Cupolas installed
  • Lightning protection installed
  • Soda lines have been run
  • Beer lines to commence this week
  • Interior natural stone install has commenced for fireplaces
  • Counter top installation has commenced
  • Cabinets are being installed
  • Arts & Craft room has been installed
  • Main bar TV feature has been constructed
  • Pizza oven finishes have commenced
  • Main kitchen equipment has been delivered and being installed
  • Turn kitchen equipment has been delivered and being installed
  • Interior tile install on going
  • Mens/Womens lockers have been installed
  • Exterior stone pavers for portico have been installed
  • Exterior stone pavers for Porte’ Cochere’ have been installed
  • Exterior stone pavers for lower patio have been installed
  • Exterior stair pavers have been installed
  • Exterior stone install at 75%
  • Cart barn concrete pad installed
  • Exterior site work/paving has commenced

09072016-ipad-2131
water-heaters

beer-taps

beer-cooler

womens-lounge

mens-restroom-doors-installed

turn-bar-window

golf-simulator-room

golf-shop

img_5131 stairs

billards-room

billards-truss

main-bar

driving-range

trusses

bar-top-being-installed

club-dining-area

coat-room-door

entry-foyer